Level Crossing Track and Civil Works

Date
October 2018
Client
Urban Passenger Operator
State
vic

Over a 4 day occupation McLeod Rail completed 272 metres of full depth track formation reconstruction, 392 metres of rerailing and associated destressing, removal and reinstatement of an asphalt crossing, removal of a pedestrian crossing and redundant signalling assets, removal of cantilever foundations, production tamping and drainage works. Over 3,000 hours of work was completed, and 110 cables and services located with no services strikes. Almost 100 personnel inducted to site.